Welcome to the Berkel & COmpany Website

atlanta stadium

New Stadium Project

Email Print

New Stadium Project – Atlanta GA

A new Stadium, Plaza, and Bridge Extension for the city of Atlanta, the stadium will be home to the Atlanta Falcons. Berkel installed over 2100 x 18-in diameter Auger Pressure Grouted (APG) piles installed from depths of about 30-ft to over 110-ft for compression loads of 150 to 220 tons, tension loads up to 60 tons, and lateral loads up to 8.5 tons.

The Plaza and new Martin Luther King Jr. bridge structures included 24-in diameter APG piles to about the same depths and tested to 1000 tons compression load.

Additionally Berkel installed earth retaining structures for temporary and permanent project grading.

Wall Length: about 1000 Linear Feet
Supported Height: 26 Feet (Maximum)
3 System Types:

- Permanent Shoring/Temporary Wood Lagging (Future Cast-In-Place Concrete Facing)
- Permanent Shoring/Permanent Shotcrete Facing (Above Grade Cistern Location)
- Temporary Shoring/Temporary Wood Lagging

 

 

reston

Reston Station

Email Print

Reston Station - Reston, Virginia

A multi-use, urban employment canter developed around the Renton Station Metro Facility with 7 levels of underground parking. Design build shoring project to encompass an excavation of over 5 acres in size with excavation depths up to 85'. The project was designed and executed using soldier piles, lagging and tiebacks requiring 310 soldier piles and 1,200 tiebacks. The wall was used as the backform for the permanent concrete walls requiring 100% accuracy in its locations to meet the needs of the General Contractor.

 

wacker

Wacker Chemical Plant

Email Print

Wacker Chemical Plant - Charleston, Tennessee

A new polycrystalline silicon  production facility located on a 550 acre greenfield site. Design build utilizing 5,000 - 20" diameter Auger Pressure Grouted (APG) Piles up to 70' deep seated into rock. To achieve high uplift capacities in areas of shallow rock, 4.5 in. diameter rock sockets were drilled into the rock below the pile tip elevations and high strength rebar installed. To meet the fast pace schedule 5 Crane Mounted APG Drill Rigs and 4 Rock Drill Rigs were utilized. Design build methods resulted in owner savings and an expendited schedule.

apm-1 apm-2

APM Tunnel Extension – ATL Int’l Airport

Email Print


APM Tunnel Extension for the Maynard H. Jackson Terminal at Hartsfield-Jackson Atlanta International Airport

Hartsfield-Jackson Atlanta International Airport underwent a $1.2 billion dollar expansion project centered on the construction of the new Maynard H. Jackson International Terminal. Passenger access between the new International Terminal and the domestic airport facilities is primarily via underground Automated People Mover (APM) trains. The new International Terminal is located approximately ½-mile from the terminus of the existing APM tunnel. A cut-and-cover method was selected for the construction of the APM tunnel extension to allow the construction team to best address unknowns and potential obstructions. The construction of the APM extension required an excavation support system for a 450-ft long, 55-ft deep excavation across Taxiway Dixie and a 900-ft long, 35-ft deep excavation beneath the basement of existing Concourse E. The excavation under Concourse E required both excavation support and support of the existing columns over the proposed excavation zone.

 

 

Berkel Design Build

bdb2

Berkel Safety & Quality

safety

 

You are here: Home